Pilot Status & Scope Lock

Status as of 2026-05-24: Pilot complete. Scope locked for production deployment.

Target go-live: end of June 2026 (clean test pass) or end of July 2026 (if testing surfaces a second pass).

The original pilot — UI5 Web Components evaluation on ui-pilot/u0-u3-u5 (see Appendix A) — succeeded and was extended into a full UI redesign (U0–U18, all merged), an IMS rewrite on CAP Node.js, AEM decommissioning, and a QA author-preview channel. What started as "swap the shellbar for ui5-shellbar" became a complete replacement platform for developers.sap.com tutorial hosting and progress tracking.


Timeline

Milestone Date Notes
First commit (POC scaffold) 2026-04-22 VitePress + Fundamental Styles + MTA deploy
Hugo migration late April VitePress retired; see hugo-migration.md
AEM decommissioned early May Frontend now serves directly behind AppRouter; tutorials served from HANA BLOBs
IMS-on-CAP rewrite shipped mid May Java IMS replaced by CAP Node.js (../srv/); migration scripts in ../scripts/
UI pilot (U0–U18) shipped 2026-05-22 All 18 UI features merged to main
Joule + embeddings + RAG 2026-05-22 → 23 Chat, step-help FAB, personalized recommendations
Admin Analytics Explorer 2026-05-23 PR #37 merged
QA channel 2026-05-23 PRs #36/#38/#40/#41/#42/#46 merged; awaiting deploy + role-collection assignment
Search word-boundary matching 2026-05-24 main HEAD (d7c33e0)
Scope lock (this document) 2026-05-24 No new features land before testing closes
Production go-live (target A) end of June 2026 If unit + hybrid + smoke tests pass and stakeholder UAT signs off
Production go-live (target B) end of July 2026 If a second pass is needed

Calendar duration: 33 days. Active development days: 22. Total commits: 1,002.


In scope for production

This is the locked scope. Anything not listed is post-launch.

Backend — CAP Node.js (../srv/)

  • 8 services: DeveloperService, AdminService, AnalyticsService, DisplayService, ConsolidationService, ScannerService, SearchService, EventStreamService
  • Custom endpoints: /api/qrcode, /build/catalog, /build/navigator, /build/slug-mapping, /build/repo-catalog, /content/publish, /content/tutorials/:slug, /content/hashes, /content/nav, /content/rollback, /feedback/submit
  • Tutorial HTML persistence: gzip-compressed BLOBs in HANA via ContentFiles + ContentManifest (../srv/lib/content-store.js)
  • WebSocket: Socket.IO transport via @cap-js-community/websocket, namespaces /ws/display (XSUAA DisplayApp) and /ws/event-stream (anonymous) for real-time event dashboards
  • Scheduled jobs: account-merge, analytics, cleanup, content GC, ngds-retry (../srv/jobs/)
  • Audit logging (@cap-js/audit-logging) + change tracking (@cap-js/change-tracking)
  • Embeddings + RAG (TutorialEmbedding, getRelevantSteps tool, ChatSettings.ragEnabled)
  • Personalized recommendations (embedding centroid + co-completion blend)
  • ORD registration (../srv/ord-annotations.cds)

Frontends

  • Hugo public site (../hugo/) — SAP Horizon theme, Object Page tutorial layout, all 18 UI pilot features (Wizard, Cmd+K, Rating, Illustrated states, Codetabs, Glossary, Toast, Reader mode, Mermaid, Skeleton loaders, Lightbox, Side-nav, Profile timeline, Mobile sheet)
  • Admin shell (../app/admin-shell/) — sap.tnt.ToolPage with 10 Fiori Elements feature components loaded as headless components
  • Analytics Explorer (../app/analytics-explorer/) — Vue 3 SPA with Monaco SQL editor over AnalyticsService
  • Public Vue apps (../hugo-apps/) — AppSpace.vue event-themed component, QR code rendering
  • Display dashboard (../app/display-app/) — Vue+Vite event monitor with rotating views
  • Scanner (../app/scanner/) — UI5 barcode scanner using sap.ndc.BarcodeScanner

Content pipeline

  • GitHub discovery via discoverAllTutorials() (../scripts/parsers/github.ts)
  • 4-tier discovery resilience (live GitHub → cache → RepoCatalog baseline → degrade) — closed in PR #21
  • Hugo build → SHA-256 delta publish to HANA via ../scripts/publish-content.ts
  • QA channel: separate tutorials-srv-qa + tutorials-hana-qa + /tutorials-qa/* route, gated by XSUAA scope Tutorial.Author

Deployment


Out of scope (post-launch backlog)

  • AEM redirect tree migration — blocked on admin team export of /etc/redirect rules
  • Author self-service tooling beyond GitHub workflow_dispatch
  • i18n beyond en_us (developers.sap.com is English-only)
  • Notifications bell wiring (currently visual-only on shellbar)

Time invested vs. hand-developed equivalent

Actual time spent (Tom, AI-assisted)

Metric Value
Calendar duration 33 days (2026-04-22 → 2026-05-24)
Active development days 22 days with commits
Estimated working hours ~175–220 hours (8–10 hr days × 22 active days)

Codebase size (measured via scc)

Metric Value
Files 690
Total lines 137,880
Code lines 115,251
Comments 2,206
Top languages JavaScript (20.6 KLOC), TypeScript (9.3 KLOC), Vue (7.4 KLOC), CSS (7.5 KLOC), HTML (3.3 KLOC)
Documentation Markdown (49.6 KLOC), JSON config (15.5 KLOC)
Cyclomatic complexity 4,139

Hand-developed estimate (single senior full-stack developer, no AI)

Three independent estimation methods, all pointing to the same order of magnitude:

Method Estimate Basis
scc COCOMO Organic (raw effort) ~351 person-months ≈ 29 person-years 2.4 × (KLOC)^1.05; schedule normally 23 months across 15 devs, but solo eliminates parallelism
Industry LOC-per-day (50 LOC/day, conservative) ~10.5 person-years ≈ 21,000 hours Senior full-stack rate including tests, debugging, design, deployment
Industry LOC-per-day (30 LOC/day, production-grade) ~17.5 person-years ≈ 35,000 hours Adjusted for the 8-service, multi-frontend, deployment-automation, AI-integration scope

Midpoint hand-developed estimate: ~15 person-years (~30,000 working hours).

Leverage ratio

~30,000 hours hand-developed  ÷  ~200 hours actual  ≈  150× leverage

Conservative bound (~10.5 person-years hand-built): ~100×. Upper bound (~29 person-years COCOMO raw effort): ~290×.

Why the ratio is this high (and what it doesn't mean)

The leverage compounds from three project-specific factors:

  1. AI-assisted parallel worktrees. UI pilots U0–U18 ran as parallel branches with subagents executing independent feature work simultaneously. A single hand-coding developer cannot run 4 frontends in parallel.
  2. Code generation density. Fiori Elements admin apps (10 of them) and CDS annotations are highly templated; hand-writing them adds linear cost that AI handles in seconds.
  3. No legacy carry-over. AEM was decommissioned cleanly rather than refactored; IMS was rewritten rather than ported. A solo dev would more likely have kept legacy systems running and refactored incrementally — lower wall-clock leverage but lower risk.

What the ratio does not mean: that 200 hours of any developer's time can produce this output. It reflects a specific combination of domain knowledge (CAP, BTP, IMS internals, AEM context), tooling investment (worktrees, MCP servers, sap-devs CLI, hooks), and a well-bounded scope defined by an existing replacement target. A greenfield project without a reference system would not see the same multiplier.


Pre-deploy checklist (testing window)

  • Hybrid test suite green (npm run test:hybrid) on DEV HANA
  • Smoke test suite green against deployed DEV (npm run test:smoke)
  • QA channel deployed and Tutorial.Author role collection assigned to first authors
  • Author UAT on QA channel (≥1 author publishes ≥1 tutorial end-to-end)
  • Performance budget verified: ~160 KB gzipped UI5 bundle still acceptable
  • Production HANA Cloud HDI sized for content BLOBs + embeddings + audit log retention
  • AEM redirect rules exported and translated to AppRouter routes
  • Migration dry-run on prod IMS data (resumable export → import → diff via ../scripts/compare-systems.js)
  • Cutover runbook reviewed with stakeholders
  • Rollback plan documented (per-manifest content rollback exists; full revert plan TBD)

Appendix A — Original UI Pilot (U0 + U3 + U5)

Preserved for traceability. The original pilot validated UI5 Web Components as the foundation; that decision is now baked into the production scope.

Original branch: ui-pilot/u0-u3-u5 (long-since merged).

Pilot scope: adopt UI5 Web Components foundation, replace the header with ui5-shellbar, add declarative ui5-message-strip banners on tutorial pages.

Dependencies added: @ui5/webcomponents, @ui5/webcomponents-fiori, @ui5/webcomponents-icons (all ^2.22).

Key files touched:

File Change
../hugo/assets/js/ui5-bootstrap.ts New entrypoint. Selectively imports ShellBar / MessageStrip / Avatar / Popover / Button / Input / List + 12 icons. Sets sap_horizon / sap_horizon_dark based on <html data-theme> and observes mutations to keep them in sync.
../hugo/layouts/_default/baseof.html Adds <script type="module" src="ui5-bootstrap.js"> (built via Hugo js.Build).
../hugo/layouts/partials/header.html Hand-rolled fd-shellbar markup replaced by ui5-shellbar + four ui5-popover panels (Navigate, Share, Trust, User). All previous behavior preserved.
../hugo/assets/css/ui5-overrides.css New stylesheet (~0.8 KB gzipped).
../hugo/layouts/partials/tutorial-banners.html New partial. Renders ui5-message-strip for deprecated, updated (within 30 days), notice, warning frontmatter fields.

Performance budget at pilot close:

Asset Raw Gzipped
public/js/ui5-bootstrap.js (new) 730 KB 159 KB
public/css/ui5-overrides.css (new) 1.7 KB 0.8 KB
public/css/sap-fundamental.css (existing) 768 KB 86 KB

Net add per page-load: ~160 KB gzipped (one-time, cached). Has not regressed through U0–U18.

Open questions raised at pilot close — all resolved during U0–U18:

Question Resolution
Notifications bell — wire it or hide it? Visible, unwired (out-of-scope, post-launch).
Joule trigger selector update? Resolved during Joule step-help FAB shipping (PR #33, 2026-05-22).
Global search via shellbar slot? Wired to SearchService with word-boundary matching (commit d7c33e0, 2026-05-24).
Mobile breakpoint match? Validated during U18 mobile step sheet shipping (PR #31, 2026-05-22).

Appendix B — References

  • Per-feature delivery details and validation notes: project memory entries U0 through U18, plus shipped-feature project memories
  • Architecture deep-dives: this folder (docs/)
  • Improvement backlog source: improvements.md (excluded from public site)
  • Project conventions and gotchas: CLAUDE.md